Data Protection Advisor: Upgrade succeeds, but Application fails to start and must be manually restarted again to begin working

Summary: Upgrade succeeds, but the Application fails to start and must be manually restarted again to begin working.

This article applies to   This article does not apply to 

Symptoms

The Data Protection Advisor (DPA) upgrade installation completes without issue on the DPA Datastore (DS) and DPA Application (App).

After the DPA Application upgrade completes, it should run the upgrade scripts and start. In this case, the DPA Application startup fails with the message "DPA control failed to start." The DPA Application status shows it in a stopped state.

If the DPA Application is manually started again, it starts properly.

The DPA upgrade log reports:

Input validation failed for object Schedule Original message: schedule is used in DC requests datadomain/analysis. Updated definition is invalid: "Point in time" schedules are only supported

The error identifies the Data Domain data collection datadomain/analysis requests, and a schedule.

The Data Domain analysis requests are configured identically and use the same schedule. Other requests are also using this schedule.

Schedules screen

The schedule and configuration appear to be correct. This is a Point In Time schedule.

Schedule screenshot
 

Schedule Properties

Cause

This is a known defect in Data Protection Advisor.

The cause is not confirmed. It is suspected that a DPA default system schedule was accidentally modified by a user. The default system schedule is named "always."

The schedule is expected to be present and of a certain type when the DPA Application runs the upgrade scripts. This causes the error to log and the DPA App to fail to start the first time afterwards.

On the next DPA Application start attempt, the upgrade scripts are no longer run. DPA Application does not encounter this issue and starts properly.

The behavior is seen again on the next DPA upgrade.

Resolution

There is no resolution to this issue. Engineering is examining the situation.

Workaround: 
The existing DPA schedule leading to this issue must be deleted and replaced with a newly created schedule. This must be done for all data collection Requests that are using this problematic schedule.

Instructions:

  1.  In the DPA UI, examine all likely Objects (in this example, Data Domains) and identify if this Schedule is assigned.
  2. Remove this Schedule from all Requests and assign a different Schedule or create a new Schedule with identical details
  3. In the DPA UI, go to System, then Schedules.
  4. Delete the problematic Schedule (in our example, 0800-Thursday)
NOTE: Ensure that all likely Objects and the uses of the Schedule are determined and the Schedule is removed or replaced.

If any of the problematic Schedules are not removed or replaced, the data collection Request may fail or cause unpredictable behavior.

The next upgrade of DPA completes properly after completing these steps. The DPA Application should start as usual. The default system Schedule is re-created during the upgrade.

Also, examining the DPA upgrade.log should show that the error message is not seen.

If these steps do not resolve the issue or the problematic Schedule cannot be identified, contact Dell Technical Support.
Article Properties
Article Number: 000215753
Article Type: Solution
Last Modified: 26 Oct 2023
Version:  4
Find answers to your questions from other Dell users
Support Services
Check if your device is covered by Support Services.