Dell PowerEdge XR8620t Installation and Service Manual

Installing the 2U top sled on the 2U node

Prerequisites

  1. Follow the safety guidelines listed in Safety Instructions.
  2. Follow the procedure listed in Before working inside your system.

Steps

  1. Align the 2U top sled horizontally and place it on top of the 2U node.
    CAUTION:Support the 2U top sled with both hands while placing it on the 2U node.
  2. Using Phillips 1 screwdriver, tighten the side screws and front captive screw that secure the 2U top sled on the 2U node.
    Figure 1. Installing the 2U top sled on the 2U node

    This image shows installing the 2U top sled on the 2U node

Next steps

  1. Connect the sideband cables between the 1U and 2U PDBs
  2. Connect the Riser1 4x signal cables to connectors on the system board
  3. Install the side cover.
  4. Install the M.2 direct riser
  5. Install the air shroud.
  6. Install the sled cover.
  7. Follow the procedure listed in After working inside your system

Rate this content

Accurate
Useful
Easy to understand
Was this article helpful?
0/3000 characters
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please select whether the article was helpful or not.
  Comments cannot contain these special characters: <>()\