1U front-rack installation

Configure the rails that are attached to the switch.

    • NOTE: For more information, see the installation instruction labels on the rail.
    Attach the inner switch rails to the S4100F–ON Series (S4128F-ON, S4148F-ON, and S4148FE-ON) switch. Line up the rail with the mounting heads and attach the rail to the chassis. Slide the rail back until it locks into place. The following shows the detail of the front standoff with the locking tab:
    Figure 1. Switch rail attachmentIllustration of attaching the switch rail.
  1. After you install both rails, line them up on the ReadyRails. Slide the switch in until it is flush with the front of rack. About three inches before you fully insert your switch, the rail locking feature engages to keep the switch from inadvertently sliding out and falling.
    Figure 2. Front rack installationIllustration of a front rack installation.
    • NOTE: Do not the use the mounted Ready-Rails as a shelf or a workplace.
  2. Tighten the two thumb screws and rack screws.

To remove the chassis from the rack or cabinet, press in the two side-release bars on the chassis at the same time and slide the chassis forward.


Rate this content

Accurate
Useful
Easy to understand
Was this article helpful?
0/3000 characters
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please select whether the article was helpful or not.
  Comments cannot contain these special characters: <>()\