Rebooting a PowerFlex rack storage node in a two-layer deployment using the PowerFlex GUI presentation server

Use the PowerFlex GUI presentation server to reboot a PowerFlex node.

Steps

  1. Log in to the PowerFlex GUI presentation server, click the Configuration tab, and click SDS.
  2. Select the specific SDS to take offline.
  3. Click More, select Enter Maintenance Mode.
  4. Select Protected, and click Enter Maintenance Mode.
  5. Using iDRAC, reboot the PowerFlex storage-only node.
  6. Take the SDS pool out of PowerFlex maintenance mode.
  7. Verify that there are no rebuild/rebalance activities before rebooting the next node.

Rate this content

Accurate
Useful
Easy to understand
Was this article helpful?
0/3000 characters
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please provide ratings (1-5 stars).
  Please select whether the article was helpful or not.
  Comments cannot contain these special characters: <>()\